Multiobjective genetic algorithm for fuzzy flowshop scheduling problem

Bulanık akış tipi çizelgeleme problemi için çok amaçlı genetik algoritma

Pages
855–862
Publication Date
2022-10-18
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

It is shown that the algorithm produces efficient solutions for medium and large size problems in a reasonable amount of time.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:The majority of research on scheduling problems addresses only a single criterion while the majority prodution planning problems require the decision maker to consider more than a single criterion for making a decision.
📊
Key Findings & Data:The effectiveness of the algorithm is illustrated by using small size problems.
💡
Conclusion & Impact:It is shown that the algorithm produces efficient solutions for medium and large size problems in a reasonable amount of time.
🔬Design:Research Article
📍Scope:Comprehensive Sample
⚙️Variables:Domain Parameters

Abstract

The majority of research on scheduling problems addresses only a single criterion while the majority prodution planning problems require the decision maker to consider more than a single criterion for making a decision. In this paper, a problem with uncertain time parameters such as processing times and due dates in the m-machine flow shop scheduling problem, which has a big importance in nowadays manufacturing systems, is considered. Further a multiobjective approach based on genetic algorithm, optimizing fuzzy makespan, fuzzy maximum tardiness and fuzzy total flow time objectives simultaneously, is developed. The algorithm is developed to obtain efficient solutions. In this algorithm the values of the multiobjective function are expressed by using membership functions. The effectiveness of the algorithm is illustrated by using small size problems. The best parameter sets of the genetic algorithm are determined by using factorial design of experiment. It is shown that the algorithm produces efficient solutions for medium and large size problems in a reasonable amount of time.

Özet

Üretim planlama problemlerinin çoğu karar vericinin herhangi bir kararı vermeden önce birden fazla kriteri düşünmesini gerektirirken, çizelgeleme alanında yapılan çalışmaların pek çoğunda sadece bir kriter ele alınmıştır. Bu makalede günümüz imalat sistemlerinde büyük öneme sahip m-makineli akış tipi çizelgeleme probleminde işlem zamanları ve teslim tarihleri gibi zaman parametrelerinin belirsiz olduğu durum ele alınarak üretim tamamlanma zamanı, maksimum gecikme ve toplam akış zamanı amaçlarını eş zamanlı eniyileyen genetik algoritma temelli çok amaçlı bir yaklaşım geliştirilmiştir. Geliştirilen bulanık iş ve teslim zamanlı çok amaçlı genetik algoritma sonucunda amaç değerlerinin üyelik fonksiyonlarıyla ifade edildiği etkin çözümler elde edilmektedir. Geliştirilen algoritmanın etkinliği küçük boyutlu problemler kullanılarak gösterilmiştir. Genetik algoritmanın en iyi parametre değerleri faktöriyel deney tasarımı ile belirlenmiştir. Algoritmanın orta ve büyük boyutlardaki problemler için makul zamanda etkin çözümleri ürettiği gösterilmiştir.

🔖

Cite This Article

EROL, S., TEMİZ, İ. (2022). Multiobjective genetic algorithm for fuzzy flowshop scheduling problem. Gazi Üniversitesi Mühendislik Mimarlık Fakültesi Dergisi, Cilt: 22 - Sayı: 4, 855–862. https://ajindex.com/articles/524055

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (14)

  1. Pinedo, M., Scheduling:Theory, algorithms, and systems, Prentice Hall, New Jersey, A.B.D., 2002
  2. Lee, C.E. ve Chou, F.D., “A two-machine flowshop scheduling heuristic with bicriteria objective”, International Journal of Industrial Engineering,Cilt 5, No 2, 128-139, 1998
  3. Nagar, A., Heragu, S. ve Haddock, J., “A combined branch and bound and genetic algorithm based approach for a flowshop scheduling problem”, Annals of Operations Research, Cilt 63, 397-414, 1996
  4. Şerifoğlu, F.S. ve Ulusoy, G. “A bicriteria twomachine permutation flowshop problem”, European Journal of Operational Research, Cilt 107, No 2, 414-430, 1998
  5. Yeh, W.C., “A new branch-and-bound approach for the n/2/flowshop/$alpha F+beta C_{max}$ flowshop scheduling problem”, Computers and Operations Research, Cilt 26, No13, 1293-1310, 1999
  6. Neppalli, V.R., Chen, C.L. ve Gupta, J.N.D., “Genetic algorihms for the two-stage bicriteria flowshop problem”, European Journal of Operational Research, Cilt 95, No 2, 356-373, 1996
  7. Ishibuchi, H. ve Murata, T., “A Multi-objective genetic local search algorithm and its application to flowshop scheduling, IEEE Transaction on System, Man, and Cybernetics-Part C: Applications and Reviews, Cilt 28, No 3, 392-403,1998
  8. Rajendran C., “Two-stage flow shop scheduling problem with bicriteria”, Journal of the Operational Research Society, Cilt 43, No 9, 871-884, 1992
  9. Gupta, J.N.D., Neppalli, V.R. ve Werner, F., “Minimizing total flow time in a two-machine flowshop problem with minimum makespan”, International Journal of Production Economics, Cilt 69, No 3, 323-338, 2001
  10. Sayın, S. ve Karabatı, S., “A bicriteria approach to the two-machine flow shop scheduling problem”, European Journal of Operational Research, Cilt 113, No 2, 435-449, 1999
  11. Murata, T., Ishibuchi, H., ve Tanaka, H., “Multiobjective genetic algorithm and its applications to flowshop scheduling”,Computers and Industrial Engineering, Cilt 30, No 4, 957-968, 1996
  12. Daniels, R.L. ve Chambers R.J., “Multiobjective flow-shop scheduling”, Naval research Logistics, Cilt 37, 981-995, 1990
  13. Chakravarthy, K. ve Rajendran, C., “A heuristic for scheduling in a flowshop with the bicriteria of makespan and maximum tardiness minimization” Production Planning and Control, Cilt 10, No 7, 707-714, 1999
  14. Allahverdi, A., “A new heuristic for m-machine flowshop scheduling problem with bicriteria of makespan and maximum tardiness”, Computers and Operations Research, Cilt 31, No 2,