CRITICAL PATH METHOD with FUZZY ACTIVITY TIMES

Pages
371–383
Publication Date
2022-12-31
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

The results were evaluated by comparing and the importance of using fuzzy numbers instead of crisp numbers in the CPM method was revealed.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:The Critical Path Method (CPM) is very useful in planning and controlling complex projects when their activity times are known precisely.
📊
Key Findings & Data:Accordingly, due to the uncertainty and difficulties in estimating operating times, CPM may not be able to accurately and fully represent real projects.
💡
Conclusion & Impact:The results were evaluated by comparing and the importance of using fuzzy numbers instead of crisp numbers in the CPM method was revealed.
🔬Design:Research Article
📍Scope:Comprehensive Sample
⚙️Variables:Critical Path Method · Fuzzy Logic · Fuzzy Number

Abstract

The Critical Path Method (CPM) is very useful in planning and controlling complex projects when their activity times are known precisely. However, in real-life applications, the durations are foreseen in the planning phase of the project; when it is put into practice, it may vary due to various reasons such as machine breakdowns, human factors, and disruptions in material supply. Accordingly, due to the uncertainty and difficulties in estimating operating times, CPM may not be able to accurately and fully represent real projects. From this point of view, in this study, it is aimed to perform critical path analysis in a project network whose activity durations consist of triangular fuzzy numbers. In the first stage, critical path analysis and project completion time were found by using possible, optimistic and pessimistic values. Then, Yager’s ranking method was used to ranking the fuzzy numbers and the project completion time and critical path were calculated with the crisp values obtained. The results were evaluated by comparing and the importance of using fuzzy numbers instead of crisp numbers in the CPM method was revealed.

🔖

Cite This Article

SÖKMEN, Ö. Ç. (2022). CRITICAL PATH METHOD with FUZZY ACTIVITY TIMES. Journal of Scientific Reports-A, Sayı: 051, 371–383. https://ajindex.com/articles/867830

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (15)

  1. Abbasi, F. and Allahviranloo, T., (2022), Realistic solution of fuzzy critical path problems, case study: The airport’s cargo ground operation systems, Granular Computing, 1-16
  2. Shankar, N.R., Sireesha, V. and Rao, P.P.B., (2010), An analytical method for finding critical path in a fuzzy project network, International Journal of Contemporary Mathematical Sciences, 5(20), 953-962
  3. Slyptsov, A.I. and Tyshchuk, T.A., (2003), Fuzzy temporal characteristics of operations for project management on the network models basis, European Journal of Operation Research, 147, 253-265
  4. Zadeh, L.A., (1965), Fuzzy Sets, Information and Control, 8(3), 338-353
  5. Mazlum, M., (2014), CPM, PERT and with Fuzzy Logic Technical Project Management and Implementation a Business, MS Thesis, Yildiz Technical University Institute of Science, Istanbul, 113p
  6. Ozkaya, U. and Seyfi, L., (2016), A novel fuzzy logic model for intelligent traffic systems, Electronics World, 122(1960), 36-39
  7. Çevik, O. and Yıldırım, Y., (2010), An application in milk products factory with fuzzy linear programming, Karamanoglu Mehmetbey University Journal of Social and Economic Research, 1, 15-26
  8. Durucasu, H., İcan, Ö., Karamaşa, Ç., Yeşilaydın, G. and Gülcan, B., (2015), Project scheduling by means of fuzzy CPM method: An implementation in Construction Sector, Ege Academic Review, 15(4), 449-466
  9. Prade, H., (1979), Using fuzzy set theory in a scheduling problem: A case study, Fuzzy Sets and Systems, 2(2), 153-165
  10. Yao, J.S. and Lin, F.T., (2000), Fuzzy critical path method based on signed distance ranking of fuzzy numbers, IEEE Transactions on Systems, Man, and Cybernetics-Part A: Systems and Humans, 30(1), 76-82
  11. Han, T.C., Chung, C.C. and Liang, G.S., (2006), Application of fuzzy critical path method to airports cargo ground operation systems, Journal of Marine Science and Technology, 14(3), 2
  12. Chen, S.P., (2007), Analysis of critical paths in a project network with fuzzy activity times, European Journal of Operational Research, 183(1), 442-459
  13. Ke, H. and Liu, B., (2007), Project scheduling problem with mixed uncertainty of randomness and fuzziness, European Journal of Operational Research,183, 135-147
  14. Atlı, Ö. and Kahraman, C., (2013), Fuzzy critical path analysis, Sigma, 31, 128-140
  15. Bushan Rao, P.P. and Ravi Shankar, N., (2013), Fuzzy critical path analysis based on centroid of centroids of fuzzy numbers and new subtraction method, Interna