Journals / AURUM Mühendislik Sistemleri ve Mimarlık Dergisi / 2025 / Cilt: 9 Sayı: 2

Design Change Delays in Oman’s Construction Industry: Challenges and Mitigation Strategies

Umman’ın İnşaat Sektöründe Tasarım Değişikliği Gecikmeleri: Zorluklar ve Azaltma Stratejileri

Awrangzeb Atif(GIRNE AMERICAN UNIVERSITY)0009-0002-9444-9062
Maher Musallam Said Albaraami(GİRNE AMERİKAN ÜNİVERSİTESİ)0009-0004-0460-1644
Changiz Ahbab(GIRNE AMERICAN UNIVERSITY)0000-0002-0780-1375
Pages
185–195
Publication Date
2025-12-31
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

This research offers insightful information for academic authors and industry experts looking to improve project outcomes and decrease construction delays in Oman's construction sector.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:Delays in construction projects are a common obstacle to Oman's construction sector.
📊
Key Findings & Data:Finding and examining design modification elements that significantly contribute to construction delays in Oman is the main goal of this study.
💡
Conclusion & Impact:This research offers insightful information for academic authors and industry experts looking to improve project outcomes and decrease construction delays in Oman's construction sector.
🔬Design:Survey & Empirical Study
📍Scope:Comprehensive Sample
⚙️Variables:İnşaat Gecikmeleri · Tasarım Değişikliği Faktörleri · Umman İnşaat Sektörü

Abstract

Delays in construction projects are a common obstacle to Oman's construction sector. These challenges result in longer construction project timeframes and other unfavorable outcomes. One of the main causes of construction delays has also been shown to be variables connected to design changes. Finding and examining design modification elements that significantly contribute to construction delays in Oman is the main goal of this study. A thorough analysis of the literature was used to identify 77 general characteristics that cause delays as well as 73 elements relevant to design. A survey questionnaire was created using the top ten design change key variables and sent to Oman's constructing industry stakeholders. The purpose of the questionnaire was to gather information from Oman's construction industry stakeholders regarding the perceived impact and frequency of the ten design change variables. This study's Average Relative Importance Index (AVRII) research identified the main causes of project delays in Oman as being design errors, client-initiated changes, inadequate planning and scheduling. This study suggests mitigation measures based on the research findings. These techniques include better communication between design teams and stakeholders, project planning, and design review. This research offers insightful information for academic authors and industry experts looking to improve project outcomes and decrease construction delays in Oman's construction sector.

Özet

İnşaat projelerindeki gecikmeler, Umman’ın inşaat sektörü için yaygın bir engeldir. Bu zorluklar, inşaat projelerinin daha uzun sürede tamamlanmasına ve diğer olumsuz sonuçlara yol açmaktadır. İnşaat gecikmelerinin başlıca nedenlerinden birinin tasarım değişiklikleriyle ilgili değişkenler olduğu da gösterilmiştir. Bu çalışmanın temel amacı, Umman’daki inşaat gecikmelerine önemli ölçüde katkıda bulunan tasarım değişikliği unsurlarını belirlemek ve incelemektir. Gecikmelere yol açan 77 genel özellik ile tasarımla ilgili 73 unsurun belirlenmesinde kapsamlı bir literatür analizi yapılmıştır. En önemli on tasarım değişikliği değişkeni kullanılarak bir anket hazırlanmış ve Umman’ın inşaat sektörü paydaşlarına gönderilmiştir. Anketin amacı, söz konusu on tasarım değişikliği değişkeninin algılanan etkisi ve sıklığına ilişkin verilerin paydaşlardan toplanmasıdır. Bu çalışmada, Ortalama Göreceli Önem İndeksi (AVRII) yöntemi kullanılarak, Umman’daki proje gecikmelerinin başlıca nedenlerinin tasarım hataları, müşteri kaynaklı değişiklikler ve yetersiz planlama ve programlama olduğu belirlenmiştir. Araştırma bulgularına dayalı olarak, bu çalışmada bazı çözüm önerileri sunulmuştur. Bu teknikler arasında tasarım ekipleri ile paydaşlar arasında daha iyi iletişim, proje planlaması ve tasarım gözden geçirmeleri yer almaktadır. Bu araştırma, proje sonuçlarını iyileştirmek ve Umman’ın inşaat sektöründe gecikmeleri azaltmak isteyen akademisyenler ve sektör uzmanları için değerli bilgiler sunmaktadır.

🔖

Cite This Article

Atif, A., Albaraami, M. M. S., Ahbab, C. (2025). Design Change Delays in Oman’s Construction Industry: Challenges and Mitigation Strategies. AURUM Mühendislik Sistemleri ve Mimarlık Dergisi, Cilt: 9 Sayı: 2, 185–195. https://doi.org/10.53600/ajesa.1795838

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (26)

  1. Agyekum, K., Kukah, A., & Amudjie, J. (2022). The impact of COVID-19 on the construction industry in Ghana: the case of some selected firms. Journal of Engineering, Design and Technology, 222-244.
  2. Ahbab, C., Daneshvar, S., & Celik, T. (2019). Cost and Time Management Efficiency Assessment for Large Road Projects Using Data Envelopment Analysis*. Teknik Dergi, 8937-8959.
  3. Al Amri, A., & Oztemir, A. (2022). Delay Factor of Construction Projects in Oman. Technium.
  4. Al Amri, T., & Perez, M. (2020). Towards a Sustainable Construction: Delays and Cost Overrun Causes in Construction Projects of Oman. Journal of Project Management, 87-102.
  5. Al Khatib, B. (2021). Determining the Delay Factors for Reconstructed Mega-Projects Phases and Associated Challenges. Doctoral Dissertaion, University of Malaya (Malaysia).
  6. Al Maamari, A., & Khan, F. (2021). Evaluating the Causes and Impact of Change Order on Construction Projects Performance in Oman. International Journal of Research in Entrepreneurship & Business Studies, 41-50.
  7. Al Saeedi, A., & Karim, A. (2022). Major Factors of Delay in Developing Countries Construction Projects: Critical Review. Sciences, 797-809.
  8. Atif, A., & Ahbab, C. (2024). Investigation on Design Change Root Causes in Afghanistan Construction Projects. Engineering for Tomorrow, 89-95.
  9. Fashina, A., Omar, M., Sheikh, A., & Fakunle, F. (2021). Exploring the significant Factors that Influence Delays in Construction Projects in Hargeisa. Heliyon, 7(4).
  10. Gondia, A., Siam, A., El-Dakhakhni, W., & Nassar, A. (2020). Machine Learning Algorithms for Construction Projects Delay Risk Protection. Journal of Construction Engineering and Mangement, 146(1), 04019085.
  11. Hamzah, N., Khoiry, M., Arshad, I., Tawil, N., & Che Ani, A. (2011). Cause of construction delay-Theoretical framework. Procedia engineering, 490-495.
  12. Ibrahim, O., Al-Kindi, G., Qureshi, M., & Al Maghawry, S. (2022). Challenges and COnstruction Applications of Solid Waste Management in Middle East Arab Countries. Processes, 2289.
  13. Imron, M., Tjendani, H., & Witjaksana, B. (2022). Analysis Of Factors Causing Variation Order In Construction Projects Of Pt. Tatamulia Nusantara Indah Surabaya Branch Office 2018-2022 Period. Devotion: Journal of Research and Community Service, 2695-2706.
  14. Lima, L., Trindade, E., Alencar, L., Alencar, M., & Silva, L. (2021). Sustainability in the construction industry: A systematic review of the literature. Journal of cleaner production, 289, 125730.
  15. Powmya, A., Abidin, N., & Azizi, N. (2023). Determination of Contractor Strategies in Delivering Construction Projects in Oman. Journal of Construction in Developing Countries, 293-316.
  16. Robinson, J. (2024). Likert Scale. Encyclopedia of Quality of Life and Well-being Research, 3917-3918.
  17. Santos, V. R., Vitorino, T., Dias, A., & Sousa, B. (2022). Developing a safety climate assessment tool for omani construction industry. International Journal of Service Science, Management, Engineering, and Technology (IJSSMET), 24.
  18. Shah, R., Al Shereiqi, K., & Brothwick, F. (2021). A Study of Challenges and Benefits of Lean Construction (LC) Principles in Omani Construction Industry. Journal of Construction Research, 16-29.
  19. Umar, A., Al Rizeiqi, R., & Badr, A. (2020). Major Causes Assessment of Construction Delays. Journal Of Engineering, Projects and Production Management, 179-186.
  20. Viles, E., Rudeli, N., & Santilli, A. (2020). Causes of delay in construction projects: a quantitative analysis. Engineering, Construction and Architectural Management, 917-935.
  21. Ahbab, C., Daneshvar, S., & Celik, T. (2019). Cost and Time Management Efficiency Assessment for Large Road Projects Using Data Envelopment Analysis*. Teknik Dergi, 8937-8959.
  22. Al Amri, A., & Oztemir, A. (2022). Delay Factor of Construction Projects in Oman. Technium.
  23. Gondia, A., Siam, A., El-Dakhakhni, W., & Nassar, A. (2020). Machine Learning Algorithms for Construction Projects Delay Risk Protection. Journal of Construction Engineering and Mangement, 146(1), 04019085.
  24. Lima, L., Trindade, E., Alencar, L., Alencar, M., & Silva, L. (2021). Sustainability in the construction industry: A systematic review of the literature. Journal of cleaner production, 289, 125730.
  25. Robinson, J. (2024). Likert Scale. Encyclopedia of Quality of Life and Well-being Research, 3917-3918.
  26. Umar, A., Al Rizeiqi, R., & Badr, A. (2020). Major Causes Assessment of Construction Delays. Journal Of Engineering, Projects and Production Management, 179-186.