An ex-post cost - benefit analysis of bolu mountain tunnel project

Pages
—
Publication Date
2020-04-21
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

According to the results, Bolu Mountain Tunnel project is not economically feasible since the Net Present Value of the project is highly negative at % 12 discount rate level.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:\r\n This paper analyzes the feasibility of Bolu Mountain Tunnel which is one of the most costly highway projects in Turkey.
📊
Key Findings & Data:The project continued for about seventeen years and opened to use in 2007.
💡
Conclusion & Impact:According to the results, Bolu Mountain Tunnel project is not economically feasible since the Net Present Value of the project is highly negative at % 12 discount rate level.
🔬Design:Research Article
📍Scope:2007 Verileri
⚙️Variables:Cost – benefit analysis · Internal rate of return · Discount rate

Özet

\r\n This paper analyzes the feasibility of Bolu Mountain Tunnel which is one of the most costly highway projects in Turkey. The project continued for about seventeen years and opened to use in 2007. Internal Rate of Return concept is used as a decision rule to asses the net benefit stream of the project. As the tunnel construction had not finished at the deadline planned by the earliest project appraisal, the necessity of tunnel construction became controversial among the society as it requires high investment costs which are withdrawn from other resources of the economy. The analysis is conducted for a 50 year period. According to the results, Bolu Mountain Tunnel project is not economically feasible since the Net Present Value of the project is highly negative at % 12 discount rate level. The NPV and IRR figures are recalculated under different scenarios but even in the best case the figures are negative.\r\n

🔖