Dergiler / Turkish Journal of Civil Engineering / 2020 / Cilt: 31 - Sayı: 4

Assessment of the Disaster Recovery Progress through Mathematical Modelling

Sayfa
10113–10126
Yayın Tarihi
2020-07-01
DOI
—
🏛️Bu makalenin bibliyografik verileri ve tam metin bağlantısı DergiPark üzerinden sağlanmıştır.
DergiPark Kaydı ↗
✨

Yapay Zeka Hızlı Bakış & Çıkarımlar

AI Insight
⚡ TL;DR(1 Cümlede Hızlı Çıkarım)

Results of the Monte Carlo simulation demonstrate that the recovery process exhibits an S-shape, the duration of initial portion and the slope of the bulk portion being significantly governed by the level of preparedness of the community.

📌 3 Maddede Bu Makale

🎯
Amaç & Hipotez:Natural disasters, especially major earthquakes, cause widespread devastation in the built environment.
📊
Temel Bulgular & Veri:Weibull distribution is used to generate the model’s parameters.
💡
Sonuç & Katkı:Results of the Monte Carlo simulation demonstrate that the recovery process exhibits an S-shape, the duration of initial portion and the slope of the bulk portion being significantly governed by the level of preparedness of the community.
🔬Tür:Modelleme & Sayısal Simülasyon
📍Kapsam:Genişletilmiş Akademik Örneklem
⚙️Değişkenler:Disaster · recovery curve · mathematical modelling

Özet

Natural disasters, especially major earthquakes, cause widespread devastation in the built environment. Hence, the major component of the recovery in its aftermath constitutes a chain of projects starting at different times, having different costs and durations. In this study, the post disaster recovery curve modelled through a mathematical approach taking into account these properties of the projects. The approach followed is based on the project S-curve concept that provides the opportunity to simulate the progress by outlining the project spending. Well-known mathematical functions are adapted to model the project spending and the handover processes. Monte Carlo simulation is performed to evaluate the general behavior of the recovery curve using the model developed. Weibull distribution is used to generate the model’s parameters. Results of the Monte Carlo simulation demonstrate that the recovery process exhibits an S-shape, the duration of initial portion and the slope of the bulk portion being significantly governed by the level of preparedness of the community.

Abstract

Natural disasters, especially major earthquakes, cause widespread devastation in the built environment. Hence, the major component of the recovery in its aftermath constitutes a chain of projects starting at different times, having different costs and durations. In this study, the post disaster recovery curve modelled through a mathematical approach taking into account these properties of the projects. The approach followed is based on the project S-curve concept that provides the opportunity to simulate the progress by outlining the project spending. Well-known mathematical functions are adapted to model the project spending and the handover processes. Monte Carlo simulation is performed to evaluate the general behavior of the recovery curve using the model developed. Weibull distribution is used to generate the model’s parameters. Results of the Monte Carlo simulation demonstrate that the recovery process exhibits an S-shape, the duration of initial portion and the slope of the bulk portion being significantly governed by the level of preparedness of the community.

🔖

Bu Makaleye Atıf Yap

DİKMEN, S. Ü., AKBIYIKLI, R., SÖNMEZ, M. (2020). Assessment of the Disaster Recovery Progress through Mathematical Modelling. Turkish Journal of Civil Engineering, Cilt: 31 - Sayı: 4, 10113–10126. https://ajindex.com/articles/864210

📄 Tam Metin PDF Okuyucu

📄

PDF görüntüleyici hazırlanıyor...

Kaynakça (2)

  1. Bruneau, M., Chang, S., Eguchi, R. Lee, G., O’Rourke, T., Reinhorn, A., Shinozuka,M., Tierney, K., Wallace, W., von Winterfelt, D., (2003). “A framework to Quantitatively Assess and Enhance the Seismic Resilience of Communities”, EERI Spectra Journal, 19, (4), 733-752 [2] Cimellaro, G.P., Reinhorn, A.M., Bruneau, M. (2010a) “Seismic resilience of a hospital system” Structure and Infrastructure Engineering, Vol. 6, Nos. 1–2, February–April 2010, 127–144 [3] Cimellaro, G.P., Reinhorn, A.M., Bruneau, M. (2010b) “Framework for analytical quantification of disaster resilience” Engineering Structures 32 (2010) 3639–3649 [4] Cimellaro, G.P. (2016) “Urban Resilience for Emergency Response and Recovery Fundamental Concepts and Applications” Springer International Publishing Switzerland [5] Güler, H.G, Sözdinler, C.Ö., Arikawa, T., Yalçıner, A.C. (2018) “Tsunami AfetiSonrasıYapısalveYapısalOlmayanÖnlemlerveFarkındalıkÇalışmaları: JaponyaÖrneği”, TeknikDergi, 8605-8629 [6] Şengöz, A., Sucuoğlu, H., (2009) “2007 Deprem Yönetmeliğinde Yer Alan “Mevcut Binaların Değerlendirilmesi” Yöntemlerinin Artıları ve Eksileri”, Teknik Dergi, 4609-4633 [7] Yanmaz, Ö., Luş, H., (2005) “Yapı Güçlendirme Yöntemlerinin Fayda-Maliyet Analizi”, Teknik Dergi, 3497-3522 [8] Cimellaro, G.P., Reinhorn, A.M., Bruneau, M. (2006) “Quantification of Seismic Resilience”, Proceedings of the 8th U.S. National Conference on Earthquake Engineering, April 18-22,
  2. San Francisco, California, USA [9] Kenley, R. (2005), Financing Construction – Cash Flows and Cash Farming, Taylor and Francis e-Library, ISBN 0-203-46739-6. [10] Hudson, K. W. and Maunick, J. (1974). Capital expenditure forecasting on health building schemes, or a proposed method of expenditure forecast. Research report, Surveying Division, Research Section, Department of Health and Social Security, UK. [11] Hudson, K. W. and Maunick, J. (1974). Capital expenditure forecasting on health building schemes, or a proposed method of expenditure forecast. Research report, [12] Peer, S. (1982). ‘Application of cost-flow forecasting models’. Journal of the Construction Division, ASCE, Proc. Paper 17128, 108(CO2): 226–32. [13] Kenley, R., and Wilson, O. D. (1986) “A construction project cash flow model-An idiographic approach.” Construction Management and Economics, 4(3), 213–232. [14] Miskawi, Z. (1989) “An S-curve equation for project control.” Construction Management and Economics, 7(2), 115–124. [15] Khosrowshahi, F. (1991) ‘Simulation of expe