Awareness-Based Claim Notification under FIDIC and Turkish Public Procurement Framework

Ahmet Buğra Can(ANKARA YILDIRIM BEYAZIT UNIVERSITY)0009-0003-0576-507X
Sertac Oruc(ANKARA YILDIRIM BEYAZIT UNIVERSITY)0000-0003-2906-0771
Sayfa
—
Yayın Tarihi
2026-10-16
🏛️Bu makalenin bibliyografik verileri ve tam metin bağlantısı DergiPark üzerinden sağlanmıştır.
DergiPark Kaydı ↗
✨

Yapay Zeka Hızlı Bakış & Çıkarımlar

AI Insight
⚡ TL;DR(1 Cümlede Hızlı Çıkarım)

The research aims to clarify how awareness should be assessed in practice and to evaluate whether the absence of such a concept in KİSK creates legal uncertainty when compared with the FIDIC framework.

📌 3 Maddede Bu Makale

🎯
Amaç & Hipotez:The determination of the awareness date for notice is important for claim submission in construction contracts.
📊
Temel Bulgular & Veri:This research examines the notice mechanisms under the FIDIC Red Book 1999 and 2017 and compares them with the Public Procurement Contracts Law (KİSK), focusing specifically on the interpretation of the phrase “became aware or should have become aware.” Under FIDIC contracts, the Contractor may be required to act not only on actual knowledge but also on knowledge it should reasonably have acquired of the relevant event or circumstance.
💡
Sonuç & Katkı:The research aims to clarify how awareness should be assessed in practice and to evaluate whether the absence of such a concept in KİSK creates legal uncertainty when compared with the FIDIC framework.
🔬Tür:Research Article
📍Kapsam:2017 Verileri
⚙️Değişkenler:Notice · Claim · Awareness

Abstract

The determination of the awareness date for notice is important for claim submission in construction contracts. This research examines the notice mechanisms under the FIDIC Red Book 1999 and 2017 and compares them with the Public Procurement Contracts Law (KİSK), focusing specifically on the interpretation of the phrase “became aware or should have become aware.” Under FIDIC contracts, the Contractor may be required to act not only on actual knowledge but also on knowledge it should reasonably have acquired of the relevant event or circumstance. The Turkish public procurement framework does not contain a general awareness-based time-bar mechanism comparable to FIDIC. However, specific notice requirements exist, notably under Article 29 of the General Conditions of Contract for Construction Works (“YİGŞ”) for extension-of-time requests, subject to exceptions such as delays caused by the administration. Article 473 of the Turkish Code of Obligations uses the expression ‘according to all estimations’ (‘bütün tahminlere göre’) when allowing the employer to withdraw before the delivery date if it clearly becomes evident that the work will not be completed on time; it does not create an awareness-based notice trigger. The comparative analysis demonstrates that this difference between FIDIC and KİSK leads to divergent approaches in determining the correct notice date, claim submissions, and dispute resolution. The research aims to clarify how awareness should be assessed in practice and to evaluate whether the absence of such a concept in KİSK creates legal uncertainty when compared with the FIDIC framework.

🔖

Bu Makaleye Atıf Yap

Can, A. B., Oruc, S. (2026). Awareness-Based Claim Notification under FIDIC and Turkish Public Procurement Framework. Turkish Journal of Engineering, Volume: 10 Issue: 4. https://doi.org/10.31127/tuje.1965194

📄 Tam Metin PDF Okuyucu

📄

PDF görüntüleyici hazırlanıyor...

Kaynakça (20)

  1. Özyiğit, S. (2022). Claim notices under the FIDIC contracts: A comparison of civil law and common law perspectives. Yeditepe University Faculty of Law Journal, 19(3), 391–448.
  2. Bilir Mahçiçek, S., Balkanlı Eryiğit, N., Yaylan Sevimli, B., & Gürcanlı, G. E. (2021). FIDIC sözleşmeleri’ndeki yeniliklerin değerlendirilmesi ve eski versiyonlarla karşılaştırılması. El-Cezerî Journal of Science and Engineering, 8(1), 504–518. https://doi.org/10.31202/ecjse.831876
  3. Oteifa, S. A., & Abu Dief, M. I. (2016). Application of FIDIC contracts in construction claims and arbitration. International Journal of Recent Scientific Research, 7(9), 13351–13356.
  4. Kalogeraki, M., & Antoniou, F. (2024). Claim management and dispute resolution in the construction industry: Current research trends using novel technologies. Buildings, 14(4), Article 967. https://doi.org/10.3390/buildings14040967
  5. Şener, B. (2023). Yüklenicinin süre uzatım ve ek ödeme taleplerine ilişkin FIDIC Kırmızı Kitap 20/2. maddede öngörülen 28 günlük süre sınırlamasının Türk Borçlar Kanunu’nda yer alan genel işlem koşulları bakımından değerlendirilmesi. Marmara Üniversitesi Hukuk Fakültesi Hukuk Araştırmaları Dergisi, 29(1), 783–809. https://doi.org/10.33433/maruhad.1262934
  6. Eren, F. (2019). Borçlar hukuku: Genel hükümler (24th ed.). Yetkin Yayınları.
  7. FIDIC. (1999). Conditions of contract for construction for building and engineering works designed by the employer (1st ed.). Fédération Internationale des Ingénieurs-Conseils.
  8. FIDIC. (2017). Conditions of contract for construction for building and engineering works designed by the employer (2nd ed.). Fédération Internationale des Ingénieurs-Conseils.
  9. FIDIC. (2000). The FIDIC contracts guide: Conditions of contract for construction; conditions of contract for plant and design-build; conditions of contract for EPC/turnkey projects (1st ed.). Fédération Internationale des Ingénieurs-Conseils.
  10. FIDIC. (2022). FIDIC contracts guide to the construction, plant and design-build and EPC/turnkey contracts (2nd ed.). Fédération Internationale des Ingénieurs-Conseils.
  11. Naji, K. K., Mansour, M. M., & Gunduz, M. (2020). Methods for modeling and evaluating construction disputes: A critical review. IEEE Access, 8, 45641–45652. https://doi.org/10.1109/ACCESS.2020.2976109.
  12. Bdaiwi, Y. M., & Skaik, S. (2019). Suitability of the new extension of time procedures under FIDIC 2017 Red Book. Construction Law Journal, 35(6), 366–383.
  13. Republic of Türkiye. (2011). Türk Borçlar Kanunu [Turkish Code of Obligations] (Law No. 6098). Resmî Gazete, 4 February 2011, No. 27836.
  14. Republic of Türkiye. (2002). Kamu İhale Sözleşmeleri Kanunu [Public Procurement Contracts Law] (Law No. 4735). Resmî Gazete, 22 January 2002, No. 24648.
  15. Public Procurement Authority. (2009). Yapım İşleri Genel Şartnamesi [General Conditions of Contract for Construction Works], Annex 8 to the Yapım İşleri İhaleleri Uygulama Yönetmeliği. Resmî Gazete, 4 March 2009, No. 27159 (Mükerrer), as amended.
  16. Bilgetekin, N. T. (2020). İnşaat sözleşmelerinde süre uzatımı ve FIDIC sözleşmelerindeki görünümü (1st ed.). On İki Levha Yayıncılık.
  17. Gök, Y. (2007). 4735 sayılı Kamu İhale Sözleşmeleri Kanunu kapsamında yapım sözleşmeleri uygulama esasları. İlksan Matbaası.
  18. Court of Cassation of Türkiye (Yargıtay), 15th Civil Chamber. (2012, December 10). Decision E. 2012/2617, K. 2012/7720 [Court decision, in Turkish].
  19. Devran, B. (2026). İNŞAAT SÖZLEŞMELERİNDE İDARİ SEBEPLE SÜRE UZATIMI. Ankara Barosu Dergisi, 84(1), 407-445. https://doi.org/10.30915/abd.1755439
  20. Republic of Türkiye. (2001). Türk Medeni Kanunu [Turkish Civil Code] (Law No. 4721). Resmî Gazete, 8 December 2001, No. 24607.