Cut - Cover Tunnelling in Adana Light Rail Transit System

ADANA HAFİF RAYLI TAŞIMA SİSTEMİNDEKİ AÇ KAPA TÜNELLERİ

Pages
31–39
Publication Date
2003-09-01
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

Groundwater inflows was determined to be as high as 10"1-10"4 m/s in water bearing terrace-calich unit in this part of tunnel

📌 3 Key Takeaways

🎯
Objective & Hypothesis:The geotechnique applications of cut-cover tunnelling in Adana Light Rail Transit System (Metro) which is constructed by Adana Metropolitan and a consortium were determined in this study.
📊
Key Findings & Data:The cut-cover tunnelling of 5 m in diameter and 1,13 km in length was advanced through Quaternary and Tertiary rock units.
💡
Conclusion & Impact:Groundwater inflows was determined to be as high as 10"1-10"4 m/s in water bearing terrace-calich unit in this part of tunnel
🔬Design:Research Article
📍Scope:Comprehensive Sample
⚙️Variables:Aç-kapa Tünelleri · Metro · Zayıf Kaya

Abstract

The geotechnique applications of cut-cover tunnelling in Adana Light Rail Transit System (Metro) which is constructed by Adana Metropolitan and a consortium were determined in this study. The project involved complex soil-structure interaction and geometry, and variable ground activities condition. The cut-cover tunnelling of 5 m in diameter and 1,13 km in length was advanced through Quaternary and Tertiary rock units. UCS, unit volume weight, Atteberg limits, compacting tests were conducted on the rock and soil samples which were obtained from drilling in the tunnelling route. Groundwater inflows was determined to be as high as 10"1-10"4 m/s in water bearing terrace-calich unit in this part of tunnel

Özet

Bu çalışmada Adana Büyükşehir Belediyesi ile oluşturulan konsorsiyum tarafından inşaa edilmekte olan Adana Hafif Raylı Taşıma Sistemi (Metro) içerisinde yapılan aç-kapa tünellerinin jeoteknik uygulamaları ele alınmıştır. Metro projesinde zeminin çok değişken ve zemin/yapı ilişkisinin oldukça karmaşık olduğu tespit edilmiştir. Aç-kapa tünelleri 5 m çapında ve 1.13 km uzunluğunda olup Kuvaterner ve Tersiyer yaşlı kaya kütleleri içerisinde açılmaktadır. Güzergah boyunca yapılan sondajlardan elde edilen zemin numunelerinde tek eksenli basma dayanımı, birim hacim ağırlığı, Atteberg limitleri, sıkışma (proktor) deneyleri ve sonuçlarının değerlendirilmesi yapılmıştır. Tünelde taraça ve kaliç birimlerinde su akış hızının 10"1 ve 10"4 m/s olduğu belirlenmiştir

🔖

Cite This Article

YAŞAR, E., ERDOĞAN, Y., ÇELİK, A. G., TAPINÇ, A. (2003). Cut - Cover Tunnelling in Adana Light Rail Transit System. Scientific Mining Journal, Cilt: 42 Sayı: 3, 31–39. https://ajindex.com/articles/954068