REVIEW OF RISKS ASSOCIATED WITH RENOVATION & MODERNIZATION OF THERMAL POWER PLANTS IN INDIA

Pages
169–175
Publication Date
2017-06-30
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

Hence it is important to understand the major risks associated with the implementation of R & M projects and mitigate them proactively to enhance the effectiveness of this approach.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:Renovation and Modernization (R&M) refers to a set of activities intended to improve the performance and reliability of the existing production facilities, and is seen as a cost-effective alternative to increase the operational life of plants.
📊
Key Findings & Data:The study aims at of Renovation and Modernization R&M of existing thermal power plants, which as an alternative can help the Country not only to increase the existing capacity and efficiency but will further help to reduce the heavy dependence on coal.
💡
Conclusion & Impact:Hence it is important to understand the major risks associated with the implementation of R & M projects and mitigate them proactively to enhance the effectiveness of this approach.
🔬Design:Research Article
📍Scope:Comprehensive Sample
⚙️Variables:Risks · effectiveness · efficiency

Abstract

Renovation and Modernization (R&M) refers to a set of activities intended to improve the performance and reliability of the existing production facilities, and is seen as a cost-effective alternative to increase the operational life of plants. Through R&M, obsolete generation equipment undergoes technological upgrades to boost capacity and reduce harmful emissions. It consists of a five-step process of identification, assessment, planning, execution and closure in order to plan, implement and monitor the entire procedure. The R&M cost per Megawatt (MW) varies, depending on the age of plant, operational history, fuel type, demand of the equipment to be replaced, the cost of generation and technology. The study aims at of Renovation and Modernization R&M of existing thermal power plants, which as an alternative can help the Country not only to increase the existing capacity and efficiency but will further help to reduce the heavy dependence on coal. Hence it is important to understand the major risks associated with the implementation of R & M projects and mitigate them proactively to enhance the effectiveness of this approach.

🔖

Cite This Article

Bajpai, P., Iyer, K. C. (2017). REVIEW OF RISKS ASSOCIATED WITH RENOVATION & MODERNIZATION OF THERMAL POWER PLANTS IN INDIA. PressAcademia Procedia, Cilt: 5 - Sayı: 1, 169–175. https://ajindex.com/articles/842593

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (6)

  1. Ahluwalia, Montek Singh (2011), “Prospects and Policy Challenges in the Twelfth Plan”, www.planningcommission.nic.in/aboutus/speech/spemsa/spe_21052011.pdf. Bagchi, Amaresh (2007), “Role of Planning and the Planing Commission in the New Indian Economy; Case for a Review”, Economic & Political Weekly, Vol.42, No. 44 (Nov. 3-9, 2007), pp. 92-100.
  2. Batra, R K and S K Chand (2011), “India’s coal reserves are vastly overstated: is anyone listening” The Energy and Resources Institute, New Delhi. Banker, R.D., A. Charnes and W. W. Cooper, 1984, Some models for estimating technical and scale efficiencies in data envelopment analysis. Management Science 30:1078–1092.
  3. Barros, C.P. and N.Peypoch, 2008, Technical efficiency of thermoelectric power plants. Energy Economics 30: 3118-3127. CEA, 2005. Technical Standard on Operation Norms for Coal/Lignite Fired Thermal Power Stations.Central Electricity Authority, Government of India. CERC, 2000a.
  4. Availability Based Tariff, Petition No.2/1999. Central Electricity Regulatory Commission. CERC, 2000b. Operational Norms for Thermal Generation, Petition No. 4/2000, Central Electricity Regulatory Commission. 〈http://〉cercind.gov.in/2612/Order%20Final.pdf CERC, 2003. Operational norms for thermal generation, Petition No. 4/2000, Central Electricity Regulatory Commission. 〈http:// www.cercind.gov.in/280203/4-00.pdf〉. Chikkatur, Ananth P (2008), “Coal Initiative Reports: A Resource and Technology Assessment of Coal Utilization in India”, Pew Center on Global Climate Change. Chikkatur, Ananth P. et al, (2009), “Sustainable development of the Indian coal sector”, Energy 34 (2009), pp. 942-953. CEA, 2013,Study Report on developing Markets for Implementation of R&M Schemes in Thermal Power Stations in India, India: Coal Fired Generation Rehabilitation Project Chand, S.K., Sarkar, S.K., 2006. Demystifying Coal Security. Economic Times, 14 April. Chikkatur, A., 2005. Making the best use of India’s coal resources. Economic and Political Weekly 40, 5457–5461. Central ElectricityAuthority,2006. All India Electricity Statistics. General Review, 2004–2005.
  5. Central Electricity Authority, Ministry of Power, Government of India. Available online /http://www.cea.nic.in/S. Central ElectricityAuthority,2008a.17th Electric Power Survey,2007.Central Electricity Authority, Ministry of Power, Government of India. Central Electricity Authority, 2008b. Thermal Performance Review,2007–2008.
  6. Central Electricity Authority, Ministry of Power, Government of