Bir dikim atölyesinde bütünleşik kapasite artırımı ve çizelgeleme kararları

Integrated capacity expansion and scheduling decisions in a sewing workshop

Pages
366–372
Publication Date
2022-10-18
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

The results are discussed together with future research directions.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:In this study, we consider the integrated problem of capacity expansion planning and job/machine scheduling in a sewing workshop.
📊
Key Findings & Data:The separate problems have been studied before; however the important integrated decision has not been previously dealt with.
💡
Conclusion & Impact:The results are discussed together with future research directions.
🔬Design:Modeling & Simulation
📍Scope:Comprehensive Sample
⚙️Variables:Domain Parameters

Abstract

In this study, we consider the integrated problem of capacity expansion planning and job/machine scheduling in a sewing workshop. The separate problems have been studied before; however the important integrated decision has not been previously dealt with. We model the problem mathematically and develop an iterative solution approach to aid the decision maker. We demonstrate the execution of the approach on a sewing workshop example. The results are discussed together with future research directions.

Özet

Bu çalışmada bir dikim atölyesinde kapasite artırımı ve iş/makine çizelgeleme problemleri bütünleşik olarak ele alınmıştır. Literatürde bu problemler ayrı ayrı çalışılmış olsa da bütünleşik yaklaşımı içeren bir çalışmaya rastlanmamıştır. Problem matematiksel olarak modellenmiş ve karar vericiye yardımcı olacak tekrarlı bir çözüm yaklaşımı geliştirilmiştir. Geliştirilen yaklaşımın çalışma ilkeleri bir dikim atölyesi örneği üzerinde gösterilmiştir. Sonuçlar gelecek çalışma konusu öneriyle birlikte tartışılmıştır.

🔖

Cite This Article

ELİİYİ, D. T. (2022). Bir dikim atölyesinde bütünleşik kapasite artırımı ve çizelgeleme kararları. Tekstil ve Konfeksiyon, Cilt: 20 - Sayı: 4, 366–372. https://ajindex.com/articles/596931

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (1)

  1. Richardson J., 1996, "Vertical integration and rapid response in fashion apparel", Organization Science, 7, 400-412. 2.Jain A.S., Meeran S., 1999, "Deterministic job-shop scheduling: Past, present and future", European Journal of Operational Research, 113,390-434. 3.Heizer J., Render B., 2006, Principles of Operations Management, 7th Ed., Prentice Hall, New Jersey. 4.Eliiyi D.T., 2004, "Operational Fixed Job Scheduling Problem", Ph.D. Thesis, Industrial Engineering Department, Middle East Technical University, Ankaira, Turkey. 5.Eliiyi D.T., Azizoğlu M., 2006, "Spread time constraints in operational fixed job scheduling", International Journal of Production Research, 44, 4343-4365. 6.Eliiyi D.T., Azizoğlu M.j 2009, "A Fixed Job Scheduling Problem with Machine-Dependent Job Weights", International Journal of Production Research, 47, 2231 - 2256. 7.Eliiyi D.T., Azizoğlu M., 2009, "Working time constraints in operational fixed job scheduling", International Journal of Production Research, in press. 8.Kroon L.G., Salomon M., Van Wassenhove L.N., 1995, "Exact and Approximation Algorithms for the Operational Fixed Interval Scheduling Problem", European Journal of Operational Research, 82, 190-205. 9.Kroon L.G., Salomon M., Van Wassenhove L.N., 1997, "Exact and Approximation Algorithms for the Tactical Fixed Interval Scheduling Problem", Operations Research, 4, 624-638. 10.Arkin A.M., Silverberg E.L., 1987, "Scheduling Jobs with Fixed Start and End Times", Discrete Applied Mathematics, 18, 1-8. 11.Kolen A.J.W., Kroon L.G., 1991, "On the Computational Complexity of (Maximum) Class Scheduling", European Journal of Operational Research, 54, 23-38. 12.Kolen A.J.W., Kroon L.G., 1992, "License Class Design: Complexity and Algorithms", European Journal of Operational Research, 63, 432-444. 13.Kovalyov M.Y., Ng C.T., Cheng T.C.E., 2007, "Fixed interval scheduling: Models, applications, computational complexity and algorithms", European Journal of Operational Research, 178, 331-342. 14.Kolen A.J.W., Lenstra J.K., Papadimitriou C.H., Spieksma F.C.R., 2007, "Interval scheduling: A survey", Naval Research Logistics, 54, 530 - 543. 15.Bouzina K.I., Emmons H., 1996, "Interval Scheduling on Identical Machines", Journal of Global Optimization, 9, 379-393. 16.Eliiyi D.T., Korkmaz A.G., Çiçek A.E., 2009, "Operational Variable Job Scheduling with Eligibility Constraints: A Randomized Constraint-Graph-Based Approach", Technological and Economic Development of Economy, 15, 245 - 2