As a result, less reinforcement and less concrete were needed and the cost was lowered

📌 3 Key Takeaways

🎯
Objective & Hypothesis:In this study, firstly, line drilling, smooth blasting and presplitting, which are known as controlled blasting techniques; are described in detail.
📊
Key Findings & Data:Then, the applications of line drilling and smooth blasting in the T2 tunnel on the Tarsus Crossing-Gaziantep Motorway are given as an example.
💡
Conclusion & Impact:As a result, less reinforcement and less concrete were needed and the cost was lowered
🔬Design:Research Article
📍Scope:Comprehensive Sample
⚙️Variables:Hat Delme · Son-Kesme · Ön-Kesme

Abstract

In this study, firstly, line drilling, smooth blasting and presplitting, which are known as controlled blasting techniques; are described in detail. Then, the applications of line drilling and smooth blasting in the T2 tunnel on the Tarsus Crossing-Gaziantep Motorway are given as an example. Fracturing beyond the excavation line and over breaking were minimised with a successful application of line drilling and smooth blasting in the T2 tunnel. As a result, less reinforcement and less concrete were needed and the cost was lowered

Özet

Bu çalışmada, önce kontrollü patlatma yöntemleri olarak bilinen hat delme, son-kesme ve ön-kesme detaylı olarak anlatılmıştır. Sonra Tarsus Ayrımı-Gaziantep Otoyolu T2 tünelinde son-kesme ve hat delme uygulamaları örnek olarak verilmiştir. T2 tünelinde başarılı bir son-kesme ve hat delme uygulaması ile kazı hattı dışındaki kayaçta çatlamalar ve aşın kazı en aza indirilmiştir. Bunun sonucunda tahkimat ve püskürtme beton kullanımı azaltılmış ve maliyet düşürülmüştür

🔖

Cite This Article

KAHRAMAN, S., KILIÇ, A. (2000). Controlled Blasting Techniques and The Application of The T2 Tunnel on The Tarsus Crossing-Gaziantep Motorway. Bilimsel Madencilik Dergisi, Cilt: 39 - Sayı: 2, 11–22. https://ajindex.com/articles/58799