Turkish building construction contracts vs. FIDIC contracts

Pages
107–118
Publication Date
2022-10-19
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

The results show that the timing of the payments is similar to those in FIDIC general conditions, yet time extension is mostly awarded for force majeure only.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:Contract administration is one of the most important pillars of a construction project.
📊
Key Findings & Data:In this study, 304 bespoken contracts undertaken in the Turkish building construction market are analyzed and compared against standard FIDIC conditions.
💡
Conclusion & Impact:The results show that the timing of the payments is similar to those in FIDIC general conditions, yet time extension is mostly awarded for force majeure only.
🔬Design:Research Article
📍Scope:Comprehensive Sample
⚙️Variables:Domain Parameters

Abstract

Contract administration is one of the most important pillars of a construction project. Its effect starts at bidding and lasts until the end of the guarantee period. A common mistake made by construction owners is structuring the construction contract in a way that minimizes the owner’s risks by relaxing the timing of owner payments, including heavy penalty clauses, requesting bank guarantees with indefinite duration, etc. However, a well-balanced construction contract may protect the work against any unexpected events, avoid potential disputes between the parties, and provide contract clauses that are fair to both parties. Being one of the pioneers in this area, the aim of this study is to compare the time and payment-related clauses of the Turkish bespoken construction contracts with standard FIDIC contracts and provide important insights and guidelines to practitioners. In this study, 304 bespoken contracts undertaken in the Turkish building construction market are analyzed and compared against standard FIDIC conditions. The results show that the timing of the payments is similar to those in FIDIC general conditions, yet time extension is mostly awarded for force majeure only. The majority of the projects were delayed in most cases observed independently from the type of contract and wording of the time extension clause. Recommendations are made to structure a more balanced building construction contract and more successful construction project management in Turkey.

🔖

Cite This Article

SÜMER, L., ARDITI, D. (2022). Turkish building construction contracts vs. FIDIC contracts. Journal of Construction Engineering, Management & Innovation (Online), Cilt: 5 - Sayı: 2, 107–118. https://ajindex.com/articles/562246

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (11)

  1. A guide to the project management body of knowledge (PMBOK guide), Project Management Institute, Newtown Square, Pa, USA, 2017
  2. Xie H, Liu H (2017) Studying Contract Provisions of Shared Responsibilities for Integrated Project Delivery Under National and International Standard Forms. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 9(3): 04517009
  3. Pettit D (2012) Effect of the New Australian Consumer Law on the Use of Standard-Form Contracts within the Australian Construction Industry. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 4(1): 1-9
  4. Lee J, Ham Y, Yi, JS, Son J (2020) Effective Risk Positioning through Automated Identification of Missing Contract Conditions from the Contractor’s Perspective Based on FIDIC Contract Cases. Journal of Management in Engineering 36(3): 05020003
  5. Youssef A, Osman H, Georgy M, Yehia N (2018) Semantic risk assessment for ad hoc and amended standard forms of construction contracts. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 10(2): 04518002
  6. El-Hoteiby AI, Hosny OA, Waly AF (2017) Particular Conditions to Cover Potential Risks of Construction Projects. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 9(3): 05017002
  7. Abotaleb IS, El-Adaway IH (2017) Administering Employers’ Payment Obligations under National and International Design-Build Standard Forms of Contract. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 9(2): 04517003
  8. Fawzy SA, El-Adaway IH (2012) Contract Administration Guidelines for Managing Conflicts, Claims, And Disputes Under World Bank–Funded Projects. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 4(4): 101-110
  9. Hamie JM, Abdul-Malak MAU (2018) Model Language for Specifying the Construction Contract’s Order-Of-Precedence Clause. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 10(3): 04518011
  10. El-adaway I, Fawzy S, Ahmed M, White R (2016) Administering Extension of Time Under National and International Standard Forms of Contracts: A Contractor’s Perspective. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 8(2): 04516001
  11. El-Adaway IH, Vance RA, Abotaleb IS (2020) Understanding Extension of Time Under Different Standard Design-Build Forms of Contract. Journal of Legal Affairs and Dispute Resolution in Engin