Potential benefits of agile project management in improving construction project performances: A case study of Iraq

Pages
64–76
Publication Date
2022-10-19
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

We also concluded that the adverse effects of poor project performance, such as quality defects, schedule variances, cost overruns, and low productivity, could be eliminated especially in the construction industry of developing countries, through APM approaches.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:Due to poor performances in construction projects, there is a necessity to apply novel project management approaches instead of traditional ones.
📊
Key Findings & Data:As developing countries considerably suffer from poor performance in construction projects, applying new project management methods has gained more importance in these territories.
💡
Conclusion & Impact:We also concluded that the adverse effects of poor project performance, such as quality defects, schedule variances, cost overruns, and low productivity, could be eliminated especially in the construction industry of developing countries, through APM approaches.
🔬Design:Survey & Empirical Study
📍Scope:Comprehensive Sample
⚙️Variables:Domain Parameters

Abstract

Due to poor performances in construction projects, there is a necessity to apply novel project management approaches instead of traditional ones. Recently, although new project management methods have emerged and applied in different industries, the construction industry has stayed behind in implementing these techniques. The agile Project Management (APM) approach is one of these methods, and it has been highly discussed recently. As developing countries considerably suffer from poor performance in construction projects, applying new project management methods has gained more importance in these territories. Even though different studies attempted to understand the applicability of the APM, it is also necessary to explore the potential benefits of the agile methods for the construction industry. For this purpose, we surveyed 140 construction experts for the prioritization of factors and received responses on the potential advantages of the APM regarding team and project performance in construction. The results achieved from the Iraq field study demonstrate that the APM could be feasible for the construction industry and could effectively bring solutions to the project performance issues. We also concluded that the adverse effects of poor project performance, such as quality defects, schedule variances, cost overruns, and low productivity, could be eliminated especially in the construction industry of developing countries, through APM approaches.

🔖

Cite This Article

KAZAR, G., TOKDEMİR, O. B., ALMHAMDAWEE, A. (2022). Potential benefits of agile project management in improving construction project performances: A case study of Iraq. Journal of Construction Engineering, Management & Innovation (Online), Cilt: 5 - Sayı: 2, 64–76. https://ajindex.com/articles/562240

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (12)

  1. Le-Hoai L, Lee YD, Lee JY (2008) Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of Civil Engineering 12:367–377.
  2. Meng X (2012) The effect of relationship management on project performance in construction. International Journal of Project Management 30(2): 188-198.
  3. Babalola O, Item EO, Ezema IC (2019) Implementation of lean practices in the construction industry: A systematic review. Building and Environment 148: 34-43.
  4. Hire S, Sandbhor S, Ruikar K, Amarnath CB (2021) BIM usage benefits and challenges for site safety application in Indian construction sector. Asian Journal of Civil Engineering 22(7): 1-19.
  5. Lai YT, Wang WC, Wang HH (2008) AHP- and simulation-based budget determination procedure for public building construction projects. Automation in Construction 17(5): 623-632.
  6. Arefazar Y, Nazari A, Hafezi MR, Maghool SAH (2022) Prioritizing agile project management strategies as a change management tool in construction projects. International Journal of Construction Management 22(4): 678-689.
  7. Mpofu B, Ochieng EG, Moobela C, Pretorius A (2017) Profiling causative factors leading to construction project delays in the United Arab Emirates. Engineering, Construction and Architectural Management 24(2): 346-376.
  8. Ahady S, Gupta S, Malik RK (2017) A critical review of the causes of cost overrun in construction industries in developing countries. International Research Journal of Engineering and Technology 4(3): 2550-2558
  9. Al Hadithi BI. An investigation into factors causing delays in highway construction projects in Iraq. MATEC Web Conferences 2018.
  10. Waheeb RA, Andersen BS (2022) Causes of problems in post-disaster emergency re-construction projects—Iraq as a case study. Public Works Management & Policy 27(1): 61–97.
  11. Mohammed SR, Jasim AJ (2017) Study and analysis of the delay problems in Iraqi construction projects. International Journal of Science and Research 6(5): 2331–2336. https://doi.org/ 10.21275/ART20173791
  12. Hass K (2007) The blendi