Journals / Maden Tetkik ve Arama Dergisi / 2019 / Cilt: 159 - Sayı: 159

Evaluation of the alternatives for gold ore grinding circuits by using of laboratory studies results and simulation method; case study: İranian Gold Co.

Pages
219–233
Publication Date
2019-08-15
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

By considering all these factors, the Alternative 3 is selected and suggested for an efficient grinding circuit.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:In this study, simulation aided design of grinding circuit for a gold mine in Iran is presented.
📊
Key Findings & Data:For this study, the operating conditions for the processing plant are the ability to process clayey minerals and the plant throughput and the d80 of the hydrocyclone overflow (leaching tank feed), which are 125 tons per hour and 45 μm, respectively.
💡
Conclusion & Impact:By considering all these factors, the Alternative 3 is selected and suggested for an efficient grinding circuit.
🔬Design:Modeling & Simulation
📍Scope:Comprehensive Sample
⚙️Variables:Comminution / Grinding circuit · Modeling and Simulation · JKSimMet

Abstract

In this study, simulation aided design of grinding circuit for a gold mine in Iran is presented. The main parameters for the design of the grinding circuit are the ore specifications and the considered operating conditions. Ore specifications were characterized by grinding tests, which included the Drop - weigh test (A, b), the abrasion test (ta) and the Bond Work Index test (Wi). For this study, the operating conditions for the processing plant are the ability to process clayey minerals and the plant throughput and the d80 of the hydrocyclone overflow (leaching tank feed), which are 125 tons per hour and 45 μm, respectively. Simulation operations were performed using grinding parameters (A, b, ta, Wi), operating constraints (plant capacity, d80 of the hydrocyclone overflow and ability to work for clayey minerals), existing mathematical models for different types of crushers, mills and separators and JKSimMet software. By completing the simulation process, three different alternatives for the grinding circuit of the considered ore were predicted. These three alternatives have been compared and evaluated with each other in terms of specific energy consumption (kWh/t), sensitivity to operational variables and the ability to process clayey minerals. The optimal circuit must have the capability to process clayey minerals and must have the lowest specific energy consumption and the least sensitivity to operational variables. By considering all these factors, the Alternative 3 is selected and suggested for an efficient grinding circuit.

🔖

Cite This Article

GHAREHGHESHLAGH, H. H., CEBECİ, A. T., ERGÜN, Ş. L. (2019). Evaluation of the alternatives for gold ore grinding circuits by using of laboratory studies results and simulation method; case study: İranian Gold Co.. Maden Tetkik ve Arama Dergisi, Cilt: 159 - Sayı: 159, 219–233. https://ajindex.com/articles/53911

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (11)

  1. Andersen, J S. 1989. Development of a Cone Crusher Model. M.Eng.Sc Thesis, University of Queensland. Arbiter, N., Harris, C.C., Stamboltzis, G.A. 1969. Single fracture of brittle spheres. Trans. Soc. Min. Eng., AIME 244, 118–130.
  2. Austin, L. G., Klimpel, R. R., Luckie, P. T. 1984. Process Engineering of Size Reduction: Ball Milling. Society of Mining Engineers of the American Institute of Mining, Metallurgical and Petroleum Engineers (AIME) Inc, ISBN 0895204215, New York, 556 pp. Awachie, S.F.A. 1983. Development of crusher models usin g laboratory breakage data, PhD Thesis, University of Queensland. Banks, J., Carson, J., Nelson, B., Nicol, D. 2001. Discrete- Event System Simulation. Prentice Hall. p. 3. ISBN 0-13-088702-1.
  3. Bond, F.C. 1952. The third theory of comminution. Trans AIME 193, 484–494.
  4. Bond, F.C. 1961.
  5. Crushing and grinding calculations, British Chemical Engineering, 6, 6, pp: 378 - 385. Broadbent, S.R., Callcott, T.G. 1956. A matrix analysis of processes involving particulate assemblies. Phil. Trans Royal Soc. London, Ser. A 249, 99–123.
  6. Daniel, M.J. 2002. HPGR model verification and scale-up. M.Sc Thesis, School of Engineering, University of Queensland, Brisbana, Australia. Daniel M.J., Morrell S. 2004. HPGR Model Verification and Scale-up. Minerals Engineering, 17, 1149-1161.
  7. Deister, R.J. 1987. How to determine the Bond work index using lab. ball mill grindability tests. Engng. Min. J., 188, 42. Delboni, H., Marco A., Rosa, N., Maurício, G., Bergerman, Rinaldo P. Nardi. 2006. Optimisation of the Sossego Sag Mill. SAG 2006: SAG Mill Circuit. Int. Conf. on Autogenous and Semi autogenous Grinding Technology, 1: 39-50.
  8. Dunne, R., Morrell, S., Lane, G., Valery, W., Hart, S. 2001. Design of the 40 foot diameter sag mill installed at the Cadia gold copper mine. SAG 2001, mining and mineral process engineering University of British Columbia, Vancouver, Canada. Epstein, B. 1947. The Material Description of Certain Breakage Mechanisms Leading to the Logorithmic-Normal Distribution, J. Franklin Inst., 244, 471-477.
  9. Epstein, B. 1948. Logarithmico-normal distributions in the breakage of solids. Ind. Eng. Chem., 40, 2289– 2291. Ergün, L., Güulsoy, O., Can, M., Benzer, H. 2005 (June 09-12). Optimization of Çayeli (Çbi) Grinding Circuit by Modelling and Simulation. The 19th International Mining Congress and Fair of Turkey (IMCET2005),
  10. İzmir,
  11. Turkey. Gardner, R.P., Austin, L.G. 1962. A Chemical Engineering Treatment of Batch Grinding. Proceedings, First Eur