Time-Cost Trade-Off Optimization with a New Initial Population Approach

Pages
9561–9580
Publication Date
2019-11-01
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

It can produce good solutions as effective as with other techniques applied for simultaneous optimization of TCTPs.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:Considering the competitive environment in all industries, completion on time is crucial for the stakeholders of a project.
📊
Key Findings & Data:Hence, it is aimed to descend the randomness on initial population and to decrease the searching effort to catch the optimal set of time-cost alternatives in the search space.
💡
Conclusion & Impact:It can produce good solutions as effective as with other techniques applied for simultaneous optimization of TCTPs.
🔬Design:Modeling & Simulation
📍Scope:Comprehensive Sample
⚙️Variables:Construction project · time-cost trade-off problem · multi-objective optimization

Abstract

Considering the competitive environment in all industries, completion on time is crucial for the stakeholders of a project. This favorable target is achieved by finding the optimal set of time-cost alternatives and this is known as time-cost trade-off problem (TCTP) in the literature. In this study, a new initial population approach is presented to improve the quality of the optimal set of time-cost alternatives. It put a predefined number of the solutions of the single objective TCTP into the initial population of teaching learning-based algorithm, which is utilized as an optimizer for the multi-objective optimization of TCTP. Hence, it is aimed to descend the randomness on initial population and to decrease the searching effort to catch the optimal set of time-cost alternatives in the search space. The proposed methodology is tested on a series of benchmark problems and the obtained results are compared with those available in the technical literature. It can produce good solutions as effective as with other techniques applied for simultaneous optimization of TCTPs.

Özet

Considering the competitive environment in all industries, completion on time is crucial for the stakeholders of a project. This favorable target is achieved by finding the optimal set of time-cost alternatives and this is known as time-cost trade-off problem (TCTP) in the literature. In this study, a new initial population approach is presented to improve the quality of the optimal set of time-cost alternatives. It put a predefined number of the solutions of the single objective TCTP into the initial population of teaching learning-based algorithm, which is utilized as an optimizer for the multi-objective optimization of TCTP. Hence, it is aimed to descend the randomness on initial population and to decrease the searching effort to catch the optimal set of time-cost alternatives in the search space. The proposed methodology is tested on a series of benchmark problems and the obtained results are compared with those available in the technical literature. It can produce good solutions as effective as with other techniques applied for simultaneous optimization of TCTPs.

🔖

Cite This Article

TOĞAN, V., EIRGASH, M. A. (2019). Time-Cost Trade-Off Optimization with a New Initial Population Approach. Teknik Dergi, Cilt: 30 - Sayı: 6, 9561–9580. https://ajindex.com/articles/51223

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (15)

  1. Meyer, W.L., Shaffer, L.R. Extending CPM for Multiform Project Time-Cost Curves. Journal of Construction Division 91(1), 45-68, 1965
  2. De, P., Dunne, E.J., Ghosh, J.B., Wells, C.E. Complexity of the discrete time-cost trade-off problem for project networks. Operations Research 45(2), 302–306, 1997
  3. Demeulemeester, E., De Reyck, B., Foubert, B., Herroelen, W., Vanhoucke, M. New computational results on the discrete time/cost trade-off problem in Project networks. Journal of the Operational Research Society 49(11), 1153-1163, 1998
  4. Yang, H.H., Chen, Y.L. Finding the critical path in an activity network with time-switch constraints. European Journal of Operational Research 120(3), 603-613, 2000
  5. Vanhoucke, M. New computational results for the discrete time/cost trade-off problem with time-switch constraints. European Journal of Operational Research 165(2), 359-374, 2005
  6. Feng, C.W., Liu, L., Burns, S.A. Using genetic algorithms to solve construction time-cost trade-off problems. Journal of Computing in Civil Engineering 11(3), 184 –189, 1997
  7. Siemens N. A Simple CPM Time-Cost Trade off Algorithm. Management Science 17(6), 354–363, 1971
  8. Vanhoucke, M., Debels, D. The discrete time/cost trade-off problem: extensions and heuristic procedures. Journal of Scheduling 10(5), 311-326, 2007
  9. Zheng, D., Ng, S., Kumaraswamy, M. applying pareto ranking and niche formation to genetic algorithm-based multiobjective time–cost optimization. Journal of Construction Engineering and Management 131(1), 81–91, 2005
  10. Sönmez, R., Bettemir, O.H. A hybrid genetic algorithm for the discrete time-cost trade-off problem. Expert Systems with Applications 39(13), 11428-11434, 2012
  11. Anagnostopoulos, K.P., Kotsikas, L. Experimental evaluation of simulated annealing algorithms for the time-cost trade-off problem. Applied Mathematics and Computation 217(1), 260-270, 2010
  12. Yang, I.T. Performing complex project crashing analysis with aid of particle swarm optimization algorithm. International Journal of Project Management 25(6), 637-646, 2007
  13. Zhang, H., Xing, F. Fuzzy-multi-objective particle swarm optimization for time –cost – quality trade-off in construction. Automation in Construction 19(8), 1067-1075. 2010
  14. Aminbakhsh, S. Hybrid particle swarm optimization algorithm for obtaining Pareto front of discrete time–cost trade-off problem. M.Sc. Thesis, Middle East Technical University, Ankara, Turkey, 2013
  15. Aminbakhsh, S., Sönmez,