Credibility based chance constrained programming for project scheduling with fuzzy activity durations

Pages
208–215
Publication Date
2022-10-11
DOI
—
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

In this paper, a fuzzy mathematical model and its crispequivalent by using credibility measure and chance-constrained programming aregiven for project scheduling problems with fuzzy activity durations.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:This paper proposes a credibility based chance constrained programmingapproach for project scheduling problems with fuzzy activity durations where theobjective is to minimize the fuzzy project completion time.
📊
Key Findings & Data:This paper expressesthe fuzzy events such as a project activity’s duration or project completion timewith fuzzy chance constraints and the chance of a fuzzy event is illustrated withfuzzy credibility distribution.
💡
Conclusion & Impact:In this paper, a fuzzy mathematical model and its crispequivalent by using credibility measure and chance-constrained programming aregiven for project scheduling problems with fuzzy activity durations.
🔬Design:Modeling & Simulation
📍Scope:Comprehensive Sample
⚙️Variables:Domain Parameters

Abstract

This paper proposes a credibility based chance constrained programmingapproach for project scheduling problems with fuzzy activity durations where theobjective is to minimize the fuzzy project completion time. This paper expressesthe fuzzy events such as a project activity’s duration or project completion timewith fuzzy chance constraints and the chance of a fuzzy event is illustrated withfuzzy credibility distribution. Due to uncertainty in durations of a project, fuzzysets and fuzzy numbers can be used in order to illustrate the uncertainty and finda solution space for the problem. Therefore, fuzzy credibility based chanceconstraint technique is investigated for project scheduling problems with fuzzyactivity durations considering the uncertainty or chance of a fuzzy event within aclosed interval. In this paper, a fuzzy mathematical model and its crispequivalent by using credibility measure and chance-constrained programming aregiven for project scheduling problems with fuzzy activity durations.

🔖

Cite This Article

ARIK, O. A. (2022). Credibility based chance constrained programming for project scheduling with fuzzy activity durations. An International Journal of Optimization and Control: Theories & Applications (IJOCTA), Cilt: 9 - Sayı: 2, 208–215. https://ajindex.com/articles/440618

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (15)

  1. DePorter, E. L., & Ellis, K. P. (1990). Optimization of project networks with goal programming and fuzzy linear programming. Computers and Industrial Engineering, 19(1–4), 500–504.
  2. Bonnal, P., Gourc, D., & Lacoste, G. (2004). Where do we stand with fuzzy project scheduling? Journal of Construction Engineering and Management, 130(1), 114–123.
  3. Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289–306.
  4. Hapke, M., Jaszkiewicz, A., & Slowinski, R. (1994). Fuzzy project scheduling system for software development. Fuzzy Sets and Systems, 67(1), 101–117.
  5. Hapke, M., & Slowinski, R. (1996). Fuzzy priority heuristics for project scheduling. Fuzzy Sets and Systems, 83(3), 291–299.
  6. Wang, H.-F., & Fu, C.-C. (1996). Fuzzy project scheduling models under inflation condition. International Journal of Uncertainty, Fuzziness and Knowlege-Based Systems, 4(6), 497–514.
  7. Hapke, M., Jaszkiewicz, A., & Slowinski, R. (1997). Fuzzy project scheduling with multiple criteria. In IEEE International Conference on Fuzzy Systems, 3, 1277–1282.
  8. Özdamar, L., & Alanya, E. (2001). Uncertainty Modelling in Software Development Projects (With Case Study). Annals of Operations Research, 102(1–4), 157–178.
  9. Wang, J. (2002). A fuzzy project scheduling approach to minimize schedule risk for product development. Fuzzy Sets and Systems, 127(2), 99–116.
  10. Chanas, S., Dubois, D., & Zieliński, P. (2002). On the sure criticality of tasks in activity networks with imprecise durations. IEEE Transactions on Systems, Man, and Cybernetics, Part B: Cybernetics, 32(4), 393–407.
  11. Chanas, S., & Zieliński, P. (2003). On the hardness of evaluating criticality of activities in a planar network with duration intervals. Operations Research Letters, 31(1), 53–59.
  12. Pan, H., & Yeh, C.-H. (2003). Fuzzy project scheduling. In IEEE International Conference on Fuzzy Systems, 1, 755–760.
  13. Pan, H., & Yeh, C.-H. (2003). A metaheuristic approach to fuzzy project scheduling. In Lecture Notes in Artificial Intelligence (Subseries of Lecture Notes in Computer Science), 2773 PART, 1081–1087.
  14. Wang, J. (2004). A fuzzy robust scheduling approach for product development projects. European Journal of Operational Research, 152(1), 180–194.
  15. Ke, H., & Liu, B. (2004). Project scheduling problem with fuzzy activity duration times. In IEEE International Conference on Fuzzy Systems, 2, 819–823. Zieliński, P. (2005). On computing the latest starting