Journals / Journal of Sustainable Construction Materials and Technologies / 2019 / Volume: 4 Issue: 2

Discovering hidden patterns in Turkish construction projects delays related to project characteristic

İsmail Cengiz Yılmaz(ISTANBUL AREL UNIVERSITY)
Pages
—
Publication Date
2019-10-21
🏛️Bibliographic metadata and full text access for this article are provided via DergiPark.
DergiPark Record ↗
✨

AI Summary & Key Takeaways

AI Insight
⚡ TL;DR(Too Long; Didn't Read)

Also, some recommendations were presented for reducing delays by using the extracted rules.

📌 3 Key Takeaways

🎯
Objective & Hypothesis:There are delays in delivering construction projects, which have great affects in all countries' economies, due to many factors and reasons and these delays bring many negative consequences.
📊
Key Findings & Data:Checking the source of these consequences or minimizing their effects is very important in terms of time and cost savings in the construction sector, especially for countries which have a continuous improvement such as Turkey.
💡
Conclusion & Impact:Also, some recommendations were presented for reducing delays by using the extracted rules.
🔬Design:Research Article
📍Scope:Comprehensive Sample
⚙️Variables:Construction Projects · Delay Analysis · Apriori Algorithms

Abstract

There are delays in delivering construction projects, which have great affects in all countries' economies, due to many factors and reasons and these delays bring many negative consequences. Checking the source of these consequences or minimizing their effects is very important in terms of time and cost savings in the construction sector, especially for countries which have a continuous improvement such as Turkey. Determination of project factors that will cause delay, analysis of their impacts and taking protective measures will help to reduce losses. Hereby in this study, the project factors that may cause to delays are identified and some important association rules between these factors and delay are extracted by collecting the data from Turkish Public and private construction projects. Also, some recommendations were presented for reducing delays by using the extracted rules.

🔖

Cite This Article

Yılmaz, İ. C. (2019). Discovering hidden patterns in Turkish construction projects delays related to project characteristic. Journal of Sustainable Construction Materials and Technologies, Volume: 4 Issue: 2. https://doi.org/10.29187/jscmt.2019.41

📄 Full Text PDF Viewer

📄

PDF görüntüleyici hazırlanıyor...

References (48)

  1. Enshassi, A., Al-Hallaq, K., and Mohamed, S. (2006). Causes of Contractor’s Business Failure in Developing Countries: The Case of Palestine, Journal of Construction Developing Countries, 11(2), 1– 14
  2. Akogbe, R.K.T., Feng, X., Zhou, J., 2013. Importance and ranking evaluation of delay factors for development construction projects in Benin. KSCE Journal of Civil Engineering. 17 (6):1213-1222
  3. Olbak M., Naimi, S. (2016). Kentsel Dönüşüm Uygulanmış 5 Katlı İki Yapı Örneğinin Deneysel Verileri Kullanılarak Doğrusal Olmayan Analiz Yöntemleri İle Güçlendirme Sonuçlarının İrdelenmesi. İstanbul Aydın Üniversitesi Dergisi, 8 (3), 145-166
  4. Mahamid, 2011. Common Risks Affecting Time Overrun in Road Construction Projects in Palestine: Contractors’ Perspective, Australasian Journal Construction Economics Building this, vol. 13, no. 2, pp.45–53, 2011
  5. Kazaz, A., Ulubeyli, S. and Tuncbilekli, N.A., 2012. Causes of Delays in Construction Projects in Turkey, Journal of Civil Engineering and Management, 2012, 18(3): 426-435
  6. Marzouk, M.M. and El-Rasas, T.I., 2014, Analyzing delay causes in Egyptian construction projects, Journal of Advanced Research, Vol. 5 No.1, pp.49-55
  7. Trauner, J.T., Manginelli, W.A., Lowe, J.S., Nagata, M.F., Furniss, B.J., 2009. Construction Delays: understanding them clearly and Delay Analysis in Construction Analyzing them correctly
  8. Faridi, A.S., El-Sayegh, S.M., 2006. Significant factors causing delay in the UAE construction industry. Construction Management and Economics 24 (11):1167–1176
  9. Odeyinka, H.A. and Yusif, A., 1997, The causes and effects of construction delays on completion cost of housing projects in Nigeria, Journal of Financial Management of Property and Construction 1997, 2(3), 31-44
  10. Sambasivan M., Soon Y. W., 2007. Causes and Effects of Delays in Malaysian Construction İndustry, International Journal of Project Management 25 (2007) 517-526
  11. Zidane, Y.J-T., Andersen, B. 2018. The Top 10 Universal Delay Factors in Construction Projects, International Journal of Managing Projects in Business, Vol. 11 Issue: 3, pp.650-672
  12. Doloi, H., Sawhney, A., Iyer, K.C. and Rentala, S., 2012. Analysing factors affecting delays in Indian construction projects, International Journal of Project Management 30 (2012) 479–489
  13. Sunjka, B.P., Jacob, U. 2013. Significant causes and effects of project delays in the Niger Delta region, Nigeria, SAIIE25 Proceedings, 9th – 11th of July 2013, Stellenbosch
  14. Almutairi, N.S., 2016. Causes pf delays on construction projects in Kuwait according to opinion of engineers working in Kuwait, International Journal of Engineering Research and Application, ISSN: 2248-9622, Vol.6, Issue 12, (Part-3) December 2016, pp 84-96
  15. Rezaei, A., Jalal, S.,2018. Investigating the causes of delay and cost-overrun in construction industry, International Advanced Researches and Engineering Journal 02(02): 075-079, 2018
  16. Reihanifar M., Naimi, S. (2016). Proje ve Maliyet Yönetimi Yöntemleriyle Kalitenin ve Verimliliğin Artırılmasının İncelenmesi. İstanbul Aydın Üniversitesi Dergisi, 8 (29), 51-65
  17. Reihanifar M., Naimi, S. (2016). Evaluatıon of Road Constructıon Projects by Value Engıneerıng Approach as a Tool for Sustainability. International journal of ecosystems and ecology science (IJEES), 8 (2), 339-346
  18. Gülce, A.C., 2010. Veri Madenciliğinde Apriori Algoritması ve Apriori Algoritmasının Farklı Veri Kümelerinde Uygulanması, Trakya Üniversitesi Fen Bilimleri Enstitüsü, Bilgisayar Mühendisliği Ana Bilim Dalı, Yüksek Lisans Tezi
  19. Liao, C.W. and Perng, Y.H., 2007. Data mining for occupational injuries in the Taiwan construction industry. Safety Science, 46, 1091-1102
  20. Tsay, Y.J., Chiang, J.Y., 2005. CBAR: an efficient method for mining association rules. KnowledgeBased Systems 18, 99–105 21. Erpolat, S., 2012. Comparison of Apriori and FP-Growth Algorithms on Determination of Association Rules in Authorized Automobile Service Centres, Anadolu University Journal of Social Sciences, Vol. 12 No:1 (151-166) 137-146
  21. Sıramkaya, E., 2005. Veri Madenciliğinde Bulanık Mantık Uygulaması, Selçuk Üniversitesi, Fen Bilimleri Enstitüsü Yüksek Lisans Tezi
  22. Kılınç, Y., 2009. Mining Association Rules For Quality Related Data In An Electronics Company, Middle East Technical University, Industrial Engineering
  23. Doğrul, G., Akay, D., Kurt, M., 2015. Analysis of Traffic Accidents by Rules of Association, Gazi Journal of Engineering Sciences, 1/2 (2015) 265-284
  24. Söylemez, İ., Doğan A. and Özcan, U., 2016. Association Rules on Traffic Accident: Case of Ankara, Ege Academic Review, Cilt 16, Özel Sayı, 2016 ss. 11/20
  25. Enshassi, A., Al-Hallaq, K., and Mohamed, S. (2006). Causes of Contractor’s Business Failure in Developing Countries: The Case of Palestine, Journal of Construction Developing Countries, 11(2), 1– 14
  26. Akogbe, R.K.T., Feng, X., Zhou, J., 2013. Importance and ranking evaluation of delay factors for development construction projects in Benin. KSCE Journal of Civil Engineering. 17 (6):1213-1222
  27. Olbak M., Naimi, S. (2016). Kentsel Dönüşüm Uygulanmış 5 Katlı İki Yapı Örneğinin Deneysel Verileri Kullanılarak Doğrusal Olmayan Analiz Yöntemleri İle Güçlendirme Sonuçlarının İrdelenmesi. İstanbul Aydın Üniversitesi Dergisi, 8 (3), 145-166
  28. Mahamid, 2011. Common Risks Affecting Time Overrun in Road Construction Projects in Palestine: Contractors’ Perspective, Australasian Journal Construction Economics Building this, vol. 13, no. 2, pp.45–53, 2011
  29. Kazaz, A., Ulubeyli, S. and Tuncbilekli, N.A., 2012. Causes of Delays in Construction Projects in Turkey, Journal of Civil Engineering and Management, 2012, 18(3): 426-435
  30. Marzouk, M.M. and El-Rasas, T.I., 2014, Analyzing delay causes in Egyptian construction projects, Journal of Advanced Research, Vol. 5 No.1, pp.49-55
  31. Trauner, J.T., Manginelli, W.A., Lowe, J.S., Nagata, M.F., Furniss, B.J., 2009. Construction Delays: understanding them clearly and Delay Analysis in Construction Analyzing them correctly
  32. Faridi, A.S., El-Sayegh, S.M., 2006. Significant factors causing delay in the UAE construction industry. Construction Management and Economics 24 (11):1167–1176
  33. Odeyinka, H.A. and Yusif, A., 1997, The causes and effects of construction delays on completion cost of housing projects in Nigeria, Journal of Financial Management of Property and Construction 1997, 2(3), 31-44
  34. Sambasivan M., Soon Y. W., 2007. Causes and Effects of Delays in Malaysian Construction İndustry, International Journal of Project Management 25 (2007) 517-526
  35. Zidane, Y.J-T., Andersen, B. 2018. The Top 10 Universal Delay Factors in Construction Projects, International Journal of Managing Projects in Business, Vol. 11 Issue: 3, pp.650-672
  36. Doloi, H., Sawhney, A., Iyer, K.C. and Rentala, S., 2012. Analysing factors affecting delays in Indian construction projects, International Journal of Project Management 30 (2012) 479–489
  37. Sunjka, B.P., Jacob, U. 2013. Significant causes and effects of project delays in the Niger Delta region, Nigeria, SAIIE25 Proceedings, 9th – 11th of July 2013, Stellenbosch
  38. Almutairi, N.S., 2016. Causes pf delays on construction projects in Kuwait according to opinion of engineers working in Kuwait, International Journal of Engineering Research and Application, ISSN: 2248-9622, Vol.6, Issue 12, (Part-3) December 2016, pp 84-96
  39. Rezaei, A., Jalal, S.,2018. Investigating the causes of delay and cost-overrun in construction industry, International Advanced Researches and Engineering Journal 02(02): 075-079, 2018
  40. Reihanifar M., Naimi, S. (2016). Proje ve Maliyet Yönetimi Yöntemleriyle Kalitenin ve Verimliliğin Artırılmasının İncelenmesi. İstanbul Aydın Üniversitesi Dergisi, 8 (29), 51-65
  41. Reihanifar M., Naimi, S. (2016). Evaluatıon of Road Constructıon Projects by Value Engıneerıng Approach as a Tool for Sustainability. International journal of ecosystems and ecology science (IJEES), 8 (2), 339-346
  42. Gülce, A.C., 2010. Veri Madenciliğinde Apriori Algoritması ve Apriori Algoritmasının Farklı Veri Kümelerinde Uygulanması, Trakya Üniversitesi Fen Bilimleri Enstitüsü, Bilgisayar Mühendisliği Ana Bilim Dalı, Yüksek Lisans Tezi
  43. Liao, C.W. and Perng, Y.H., 2007. Data mining for occupational injuries in the Taiwan construction industry. Safety Science, 46, 1091-1102
  44. Tsay, Y.J., Chiang, J.Y., 2005. CBAR: an efficient method for mining association rules. KnowledgeBased Systems 18, 99–105 21. Erpolat, S., 2012. Comparison of Apriori and FP-Growth Algorithms on Determination of Association Rules in Authorized Automobile Service Centres, Anadolu University Journal of Social Sciences, Vol. 12 No:1 (151-166) 137-146
  45. Sıramkaya, E., 2005. Veri Madenciliğinde Bulanık Mantık Uygulaması, Selçuk Üniversitesi, Fen Bilimleri Enstitüsü Yüksek Lisans Tezi
  46. Kılınç, Y., 2009. Mining Association Rules For Quality Related Data In An Electronics Company, Middle East Technical University, Industrial Engineering
  47. Doğrul, G., Akay, D., Kurt, M., 2015. Analysis of Traffic Accidents by Rules of Association, Gazi Journal of Engineering Sciences, 1/2 (2015) 265-284
  48. Söylemez, İ., Doğan A. and Özcan, U., 2016. Association Rules on Traffic Accident: Case of Ankara, Ege Academic Review, Cilt 16, Özel Sayı, 2016 ss. 11/20.